Winda Energy is planning a wind farm in Tuohiräme, Kannus. The preliminary project area is about 1 300 hectares in size and is located in the northern part of Kannus, about 4 km north of downtown Kannus. About 15-20 wind turbines are tentatively planned for the area. The number and location of turbines will be specified through discussions with landowners and the master planning process. In addition, an environmental impact assessment (EIA) procedure will be carried out for the area. The Tuohiräme project is developed together with the Kalajoki-Linnanharju project.

Schedule

2022

Spring-Summer 2022

- Master planning agreement

- The EIA is started

2023

Autumn-Winter 2023

- Finalizing master planning proposal

2024

Autumn-Winter 2024

- Approved master plan

2025-2026

Spring 2025

- Building permits

Summer 2025

- Starting construction work