Winda Energy is planning a wind farm in Verkasalo in Alavieska, Kalajoki and Ylivieska. The preliminary project area is about 2 300 hectares in size and is located in the southern part of Alavieska, in the southeastern part of Kalajoki and in the western part of Ylivieska. About 20-30 wind turbines are tentatively planned for the area. The number and location of turbines will be specified through discussions with landowners and the master planning process. In addition, an environmental impact assessment (EIA) procedure will be carried out for the area.

Information about the project's EIA:

Verkasalo wind power project (ympäristö.fi)

News

10/2022 - Public events on the EIA program were held on 18.-20.10. in Ylivieska, Alavieska and Kalajoki

11/2021 - The city of Kalajoki has approved the master planning initiative for the Verkasalo project

05/2021 - The city of Ylivieska has approved the master planning initiative for the Verkasalo project

04/2021 - The municipality of Alavieska has approved the master planning initiative for the Verkasalo project

Schedule

2022

EIA and Master Planning underway

2023

Summer 2023

- Finalizing master planning proposals

2024

Summer 2024

- Approved master plans

Autumn 2024

- Building permits

2025-2026

Winter 2025

- Starting construction work

2025-26